OUTAGES: (800) 677-2612 | CONTACT: (217) 774-3986
Interconnection with Shelby Electric Cooperative's grid is very complex. Members considering a system should call the office and speak with a member services representative directly.
Please call the office to discuss your project prior to application. (800) 677-2612 or (217) 774-3986
Overview
Step One: Contact Us
Please contact us as a first step if you are interested in installing a renewable energy system. Our member services department can be reached by phone at 217-774-3986. We will provide you with information on our policies and answer any questions you may have.
Members who install a renewable energy system on Shelby Electric's lines must own the system themselves per cooperative bylaws. Third party ownership of the system such as Purchase Power Agreements and lease agreements tied to kWh production is not permitted.
A non-refundable application fee of $500 is required at the time of application to secure the project's placement into the queue of projects. This fee is imposed as an effort to recover costs incurred to Shelby Electric during the connection process. All projects must be reviewed by our Engineering Department before authorization to construct is granted. Additional deposits may be required depending on the system size and necessary engineering studies and/or Cooperative system upgrades.
SEC Board Policy 307: Interconnection and Parallel Operation of Distributed Generation
PLEASE NOTE: Cooperative policies are subject to change.
Check out Touchstone Energy's 10 Steps to Take Before Considering Solar as well as Questions to Ask a Solar Contractor.
Step Two: Application to Interconnect
Applying to interconnect to the Shelby Electric distribution system is a key step in the process as it provides you a position in our queue. During this phase, our Engineering Department will gather the specific characteristics of your project to use in performing an impact analysis of your system operating in parallel with our system.
Small Distributed Generation Facilities Incentive (50 kW AC or below): Attachment A, Attachment D, Attachment E, proof of $1 million liability insurance, $500 application fee, and a $1,500 Third Party Engineering Analysis deposit
*If a system below 10 kW AC requires an additional deposit, Shelby Electric will contact the member during the system study process.
Qualifying Facility (10 to 100 kW AC): Attachment A, Attachment B, Attachment C, Attachment D, Attachment E, FERC Form 556, proof of $1 million liability insurance, $500 application fee, and a $1,500 Third Party Engineering Analysis deposit
PLEASE NOTE: Additional deposits may be required depending on the system size and necessary engineering studies and/or Cooperative system upgrades.
Step Three: Approval
Once your project has been approved, Shelby Electric will notify you and your contractor that construction can begin.
If additional system upgrades are needed for your project, you will be notified at this point.
Step Four: Site Inspection/Meter Install
Once construction is complete, BEFORE the system is energized, contact our Member Services Department to make an appointment for inspection of the system. ALL projects must be inspected before authorization to energize is granted. The homeowner AND a representative of the contractor MUST be present for the inspection.
If the project passes inspection, the appropriate meter will be installed. If the Cooperative must return to the location for inspection more than two times, a non-refundable fee of $100 must be paid in advance of the 3rd scheduled inspection.
Step Five: Congratulations!
Congratulations! You are now a proud owner of a distributed generation system. Shelby Electric Cooperative will return signed copies of Attachment D and Attachment E.
Your bill will start to look different, please do not hesitate to call into our office and speak with the Member Services Department with any questions.